Afam 3 mobile power plant to provide electricity for 1.5m Nigerians

Must read

Agencyhttps://dailynigerian.com/
Jaafar Jaafar is a graduate of Mass Communication from Bayero University, Kano. He was a reporter at Daily Trust, an assistant editor at Premium Times and now the editor-in-chief of Daily Nigerian.
- Advertisement -

General Electric, GE, says the fast mobile power plant, that is still under construction at Afam 3 Power Plant, Rivers state, is a 240 MW plant that would provide electricity for 1.5million Nigerians when completed.

The Managing Director in charge of Gas Power Systems, GP, Mohammed Mijindadi, who stated this to newsmen in Afam, Rivers State, said the plant is capable of generating electricity with the use of condensate and natural gas.

“This is unique because the benefits of these units here is speed. Typically to build a power plant it takes a very long time, but with these units you can have power up and running in a very short time.

READ ALSO:   APC Crisis: Court restrains Giadom from acting as party chairman
READ ALSO:   Ex-IGP Sulaiman Abba joins APC, guns for Senate

“So that is specifically why we did this.

“I think something else that is not really mentioned is there is the ability to run both natural gas and condensate and with all the volatility in the gas system in the country, the ability to run other fuels, I think it makes it really attractive; so for this it is very good.

“On the hydro space, we also have a lot of ability to play there and also on the solar space too.

“I think we play across many of the value chain in the power space.“

Cue out audio

According to him, the project will be due for completion in July.

READ ALSO:   Eid-el-Maulud: Wike urges Muslims to promote religious tolerance

“A lot of things have been advanced on the site. On paper, we are saying July, but there are a few things on the government side which is securitisation; once it is done we are in the process of commissioning one of the units.

“And we think it can go quickly; what you see here is already done. Once the securitisation is in place, I think before July this should be up and running.“

READ ALSO:   APC Crisis: Court restrains Giadom from acting as party chairman

He further said that the design for the Afam 3 fast power project could be replicated elsewhere in the country.

“I think when we started, we tried to create a model that could be replicated elsewhere, of course with the understanding that the government might not have a lot of money to fund the building of a lot of the units.

READ ALSO:   Tug of war for Buhari, Atiku as INEC releases number of PVCs collected according to states

“So the structure I designed was a structure that if this works you could easily take it and build it in other places.

“Remember that the things you are looking for are speed, flexibility – due to the uncertainty of fuel availability – and of course financing, which is not readily available.

“So with a structure like this, without bothering the government, or GE, if you do it right you can replicate it in many places.”

NAN