COVID-19: Why Sani Abacha isolation centre construction delayed – Kano govt

Must read

Rayyan Alhassan
Rayyan Alhassanhttps://dailynigerian.com/author/rayyan/
Rayyan Alhassan is a graduate of Journalism and Mass Communication at Sikkim Manipal University, Ghana. He is the acting Managing Editor at the Daily Nigerian newspaper, a position he has held for the past 3 years. He can be reached via rayyanalhassan@dailynigerian.com, or www.facebook.com/RayyanAlhassan, or @Rayyan88 on Twitter.
- Advertisement -
tiamin rice
tiamin rice

Kano State Government on Tuesday said the delay in the early completion of the Sani Abacha Stadium, SAS, Isolation Centre was necessitated by the review of the project initial plan.

Muhammad Garba, the state Commissioner of Information, made the clarification in a statement in Kano.

Mr Garba, who was reacting to a viral social media video clip on the project, dismissed the footage as a mischievous attempt to misrepresent facts on the ongoing installation works at the isolation centre, donated by the Coalition Against COVID-19, CACOVID.

tiamin rice

The project, which was initiated in April, was designed with a 500-bed capacity for the treatment of COVID-19 patients.

Recall that the three and a half minutes video clip, showed ongoing installation works at the isolation centre with artisans working inside one of the two temporary tents

READ ALSO:   BREAKING: Nigerian govt lists conditions for reopening schools

It also showed beds and containers packed outside the tents, while a commentator alleged that the centre was not functional in spite of the hundreds of confirmed cases of the virus in the state.

Mr Garba, however, said that the video clip was an attempt to discredit the effort by the coalition in the fight against COVID-19.

“Whoever is behind the filming does so to deliberately to distort the datum considering that even in the clip, it shows that the project is still ongoing, but calculatedly moves away from filming the exercise just to accomplish the task of garbling the fact.

READ ALSO:   COVID-19: Nigeria registers 8,197 infections in 15 days
whatsApp

“The Sani Abacha Stadium Isolation Centre initially billed to accommodate 500 beds was later redesigned based on recommendation and standards set by the Presidential Task Force on COVID-19, PTF, and the Nigeria Centre for Disease Control, NCDC,” he said.

Mr Garba explained that while the project was reviewed and installation works continued, 218 of the 500 beds planned for the centre were deployed to other centres.

He listed the centres to include Abubakar Imam Urology, 77 beds; Daula Isolation Centre, 10 beds and 213 beds moved to Karfi Sports Institute.

The commissioner noted that 213 beds were retained at SAS Isolation Centre, bringing the total number of 500-bed capacity delivered by CACOVID in the state.

READ ALSO:   NCDC leads investigation as mysterious illness grips Sokoto

Mr Garba reiterated government commitment to ensure completion of the 213-bed capacity isolation centre at the stadium, in accordance with recommendation of the relevant health authorities.

He urged members of the public to disregard the video clip, stressing that government would not be distracted from the big picture to serve the people.

The Kano State Ministry of Health had confirmed 919 COVID-19 cases of which 747 were active cases, 134 discharged and 38 deaths as at May 25.

NAN