FEC approves additional N8.39bn for Tambuwal-Jega-Makera Highway

Must read

Ibrahim Ramalan
Ibrahim Ramalanhttps://dailynigerian.com/author/rayyan/
Rayyan Alhassan is a graduate of Journalism and Mass Communication at Sikkim Manipal University, Ghana. He is the acting Managing Editor at the Daily Nigerian newspaper, a position he has held for the past 3 years. He can be reached via rayyanalhassan@dailynigerian.com, or www.facebook.com/RayyanAlhassan, or @Rayyan88 on Twitter.
- Advertisement -
tiamin rice
tiamin rice

The Federal Executive Council, FEC, has approved additional N8.39 billion for the completion of the Tambuwal-Jega-Makera road traversing Sokoto and Kebbi States.

The Minister of Works and Housing, Babatunde Fashola, made the disclosure shortly after Wednesday’s virtual council meeting presided over by President Muhammadu Buhari.

According to the minister, FEC approved the request of the contractor, CRCC, for a N8.39 billion augmentation of the contract sum for the completion of the 85-kilometre Yakuri to Makera section of the road.

tiamin rice
whatsApp

He said: “The company is seeking an augmentation of the contract sum by N8.39 billion, which was approved and the reason was for price changes, essentially, between 2012 when the contract was awarded, and now.

READ ALSO:   NITDA begins digital training for 10,000 vulnerable Nigerians

“Materials and costs have changed and also the scope of works of the 85 kilometres of the road has to be changed now from rehabilitation to reconstruction because it has deteriorated from when it was awarded 12 years ago.

“There are two sections of the road because it comes all the way from Sokoto to Makera. The first section is awarded to Triacta, that section is 296 kilometres and we’ve completed it just recently.

“The entire 296 kilometres is now motorable. About 100 kilometres of the second section, which is the subject of augmentation, from Yauri to Makera, has been completed so we just have 85 kilometres to go.”