Monday, June 21, 2021

FEC approves N6.2bn for 6 electricity projects

Headline

https://dailynigerian.com/author/rayyan/
Rayyan Alhassan is a graduate of Journalism and Mass Communication at Sikkim Manipal University, Ghana. He is the acting Managing Editor at the Daily Nigerian newspaper, a position he has held for the past 3 years. He can be reached via [email protected], or www.facebook.com/RayyanAlhassan, or @Rayyan88 on Twitter.
tiamin rice

The Federal Executive Council, FEC, on Wednesday approved more than $8.29 million as well as N3 billion for execution of various electricity projects in the country.

The Minister of Power, Mamman Saleh, disclosed this to State House Correspondents after the week’s virtual FEC meeting presided over by President Muhammadu Buhari.

Mr Saleh said the projects, most of which are procurement of equipment as well as designs and manufactures, are for upgrade of the nation’s electricity facility and improvement of power supply.

According to him, the Ministry of Power presented six memoranda to the FEC, all of which were approved.

The aggregate of all the figures, in both naira and dollar denominations, summed up to a total of N6,156,168,822 when the dollar component was converted by the official exchange rate of N380 to $1.

See also  Insecurity: Buhari, state governors have failed Nigerians – CSOs
See also  INVESTIGATION: Despite ban, filing stations openly sell fuel in Daura, Jibiya border towns

“The Federal Executive Council today approved six memos under the Ministry of Power. The first one is the award of a contract for design, manufacturing and supply of critical spare parts for Crompton Greaves 330 kV, 132 kV and 33 kV circuit breakers to Messrs. Legen Engineering Nigeria Limited in the sum of N298,339,887.04.

“The second one is the award of the contract for the procurement of 50 sets of 400 AH battery banks, 30 to 50 volts and 30 number of 110 volt battery charges for the substation used by the TCN in favour of Messrs. DTS Transformers Electric Industry Limited at the sum of N644,805,953.10.

See also  Rep backs Senate’s call for deployment ex-Service Chiefs to Lake Chad region as ambassadors

“The third award of contract is for the procurement of 50 cent also of 132 kV isolators for the TCN in favour of Messrs. Leading Diagonal Engineering Nigeria Limited in the sum of $840,650 plus N53,900,000 within the delivery period of six months.

“The fourth one is the award the contract for the design, manufacturing and the supply of three 60/66 MVA 132kV power transformers with accessories and 15 number of 500 kV transformers, 33/0.415kV earthing transformers for the TCN in favour of Messrs. Zhenjiang Transformers Company Limited, in the sum of N1,296,953,044.55 with delivery period of 12 months.

See also  Buhari meets The Gambia President, Adama Barrow, at Aso Villa

“The fifth one is the award of the contract for the design, supply and installation of Optical Wire (OPGW) and Universal Optical Transportation Network System (OTN) for some critical transmission lines in favour of Messrs. Xinjiang Power and Transportation Company Limited in the sum of $6,800,743.51, plus N668,843,634.74, with a delivery period of 12 months

See also  OPEC countries lost $1trn to oil price plunge in two years, says Barkindo

“The last one is the upward review of the contraction for the design, manufacture, supply, installation and commissioning of 1X 100MVA, 132/33kV power transformers at Ogba Transmission Substation, Lagos, in favour of Messrs. Power Control and Appliances Limited, in the sum of $648,038.31, plus N48,342,524.18, with the delivery period of six months.

“All these procurements are geared towards upgrades of the transmission system, to the national grid, so that we can have sufficient power supply to the nation,” he said.

Related News

Latest News

cosgrove
atrk atrk atrk atrk atrk atrk atrk atrk atrk atrk