Rayyan Alhassan is a graduate of Journalism and Mass Communication at Sikkim Manipal University, Ghana. He is the acting Managing Editor at the Daily Nigerian newspaper, a position he has held for the past 3 years. He can be reached via rayyanalhassan@dailynigerian.com, or www.facebook.com/RayyanAlhassan, or @Rayyan88 on Twitter.
- Advertisement -
tiamin rice
tiamin rice

The Transmission Company of Nigeria, TCN, has announced that efforts to fully recover the national grid are almost complete following a partial disturbance on Monday.

The disturbance occurred at approximately 6:48 p.m., prompting immediate recovery efforts.

Ndidi Mbah, TCN’s General Manager of Public Affairs, in a statement on Tuesday, said the recovery process commenced swiftly, with Azura Power Station providing the necessary blackstart.

tiamin rice

She said by 10:24 a.m. on Tuesday, the grid recovery had reached advanced stages, in spite of encountering a brief challenge that caused a minor setback.

whatsApp

“Notwithstanding the setback, TCN continued its recovery efforts, achieving significant progress.

“Bulk power availability has been restored to approximately 90 per cent of its substations nationwide, with supply reinstated to the Abuja axis and other major distribution load centres.

READ ALSO:   Electricity consumers grew to 21.44m in 2022 — NBS

“The partial disturbance did not affect the Ibom Gas generating station, which continued to supply power to areas in the South Southern part of the country, including Eket, Ekim, Uyo, and Itu 132 kilovolt transmission substations.”