National library project to be completed in 21 months — Minister

Must read

Ibrahim Ramalan
Ibrahim Ramalan
Ibrahim Ramalan is a graduate of Mass Communications from the Ahmadu Bello University (ABU) Zaria. With nearly a decade-long, active journalism practice, Mr Ramalan has been able to rise from a cub reporter to the exalted position of an editor; first as Arts Editor with the Blueprint Newspapers before resigning in 2019; second and presently as an Associate Editor of the Daily Nigerian online newspaper. He can be reached via ibroramalan@gmail.com, or www.facebook.com/ibrahim.ramalana, or @McRamalan on Twitter.
- Advertisement -
tiamin rice
tiamin rice

The Minister of Education, Prof. Tahir Mamman has assured Nigerians that the National Library would be completed in 21 months as the nations depository.

Mr Mamman said this in Abuja on Tuesday during a tour with some Heads of Agencies in the sector to ascertain the project level.

He said that contractor in charge of the project would return to site in earnest to deliver the national edifice for the good of the citizenry.

tiamin rice

“This project is too important for Nigerians and we have this project uncompleted for close to 20 years. We know the importance of a library not to talk about a national library.

“So, the decision is that we have a president who does not tolerate uncompleted projects anywhere. He is determine to deliver on what will bring progress and development and the national library is one of the major edifice anywhere in the world.

READ ALSO:   FEC approves N487m to procure banking software for Federal Mortgage Bank

”So, the decision is that every one involved must come back to site,” he said.

When asked about the cost required to complete the project, the minister refused to comment on it, said though there were issues surrounding the project but that is being worked out as everyone involved would come together to review the cost.

“There are some issues here and there but the project will be completed in about 21 months.

”But we are urging them (Construction company) to deliver the project earlier because we’ve dragged it for too long and the project is too important for it to be dragged any further.

READ ALSO:   48 killed as petrol tanker explodes in Niger
whatsApp

”So whatever obstacles in the project, we are determined to go over it and attend to it so it doesn’t become an obstacle,” he said.

Meanwhile, the National Librarian, Prof. Chinwe Anunobi, faulted the issues of bureaucratic bottleneck to have hindered the completion of the project since awarded in 2006.

She also assured that work would commence immediately saying that the monitoring would be followed by meetings of stakeholders involved in the project.

NAN reports that the initial contract sum of the national library as at March 11, 2006 when it was first awarded was N8,590,226,393.00 when exchange rate was N130.29. The project was then expected to span through 22 months.

READ ALSO:   Citizens groan as petrol scarcity worsens in Kaduna, Katsina, Kano

The ministry of education later re-awarded the project in March 2010 for 21 months at the cost of N49,643,337,960.32.

However, the construction firm in charge of the project, Reynolds Construction Company Nigeria Ltd. had in 2010 projected N120,327,599,990.45 as cost of completion of the project.

Also, as at 2012, when exchange rate was N163, N150 million was needed for the completion of the project.

In other words, with the current exchange rate of the dollar at 774 naira per dollar, the government would be required to use over N100 billion to complete the project.

NAN