The Transmission Company of Nigeria, TCN, says it has received eight new power transformers under its Project Management Unit at the Apapa Port, Lagos.

Ndidi Mbah, General Manager Public Affairs stated this in a statement in Abuja on Thursday.

Mrs Mbah stated that the transformers were six 150/187.5 Mega Volt Ampere, MVA, 330/132/33 Kilo Volt (kV) power transformers and two  100/125MVA, 132/33kV power transformers

tiamin rice

She stated that the transformers were still at the port, adding that arrangement was being concluded to move them out.

Mrs Mbah listed the proposed locations for the transformers to include Bauchi- 2×150/187.5MVA, 330/132/33kV.

whatsApp

“1×150/187.5MVA, 330/132/33kV – Mayo Belwa, 1×150/187.5MVA, 330/132kV – Yola and 1×150/187.5MVA, 330/132/33kV —Maiduguri.

READ ALSO:   Nigerians urged to be whistle-blowers on PVC buying, selling

“1×150/187.5MVA, 330/132/33kV – Damaturu, 2×100/125MVA, 132/33kV – Yola, ” she said.

According to her, TCN through the contractor, MBH will move all the transformers to TCN Substations mentioned above.

She added that the project was among the World Bank-funded projects under Nigeria Electricity Transmission Project, NETAP.

“The transformers are part of the ongoing grid expansion projects under TCN’s Project Management Unit.