We’re working tirelessly to restore power to North-East – TCN

Must read

Ibrahim Ramalan
Ibrahim Ramalan
Ibrahim Ramalan is a graduate of Mass Communications from the Ahmadu Bello University (ABU) Zaria. With nearly a decade-long, active journalism practice, Mr Ramalan has been able to rise from a cub reporter to the exalted position of an editor; first as Arts Editor with the Blueprint Newspapers before resigning in 2019; second and presently as an Associate Editor of the Daily Nigerian online newspaper. He can be reached via ibroramalan@gmail.com, or www.facebook.com/ibrahim.ramalana, or @McRamalan on Twitter.
- Advertisement -
tiamin rice
tiamin rice

The Transmission Company of Nigeria, TCN, says its contractors are working tirelessly to erect four new transmission towers along the Jos-Gombe axis.

The company said this is to enable it restore power supply to states in the North Eastern part of the country, Ndidi Mbah, TCN’S General Manager, Public Affairs stated this in a statement in Abuja on Friday.

Mr Mbah said that the erection of the towers followed an earlier destructive attack on four transmission towers by vandals.
She said that the towers collapsed and affected Gombe, Damaturu, Maiduguri, Yola, Bauchi and Jalingo.

tiamin rice

”Immediately after the incident, TCN’s engineers worked first to redistribute available bulk supply on the Jos – Bauchi – Gombe 132 Kilo Volt (kV) line between Jos and Yola Discos.

READ ALSO:   Kano anti-graft agency won’t relent in prosecuting corrupt cases – chairman

”While work commenced immediately at reconstructing the four vandalised towers.
”Presently, we are rebuilding the four towers simultaneously. Progress is evident, with one tower nearing 80 per cent completion and another at 60 per cent,”she said.

whatsApp

According to her, the third is at 30 per cent and dismantling work finished on the fourth tower.

Mr Mbah said that additionally, tower members are being fabricated and assembled on-site to expedite construction.

She said that the company was committed to quick restoration of bulk power on the line route.
“Construction work on the Jos – Gombe transmission line, taking supply up to Damaturu and environs, will be completed and energised by the May 20 while the Damaturu – Maiduguri axis will be completed on May 27.

READ ALSO:   NNPC profit rises to N674bn in 2021

”Expectedly, bulk power transmission will be fully restored on the affected 330kV transmission line by May 27, Yola and Jos DisCos will also be able to offtake and distribute optimally from TCN substations.
”For now, only 38 Megawatts (MW) is wheeled to both Jos and Yola Distribution companies, with each receiving 19MW each,” she said.

Mr Mbah said that efforts to take some of the available power to Jalingo was hampered by very high voltage on the line, which could cause a system disturbance.
She said that TCN was aware of the inconveniences resulting from the current inadequate power supply through Yola, and Jos DisCos to electricity customers in the affected states.

READ ALSO:   Kagara abduction: 27 schoolboys, 3 staff, 12 family members missing

Mr Mbah said that the company pledged to earnestly expedite work on the towers, to ensure that they are completed within the time frame indicated.